DECEMBER 9TH, 2010-JANUARY 8TH, 2011

• 3,940 m3 of mass and structural excavation has been performed on Section 2b;
• 193 m3 of surface drainage concrete and 130 m3 of structural concrete have been placed on Section 2b;
• 10 m3 of surface drainage concrete and 557 m3 of structural concrete have been placed on Section 3c;
• 19,591m3 of mass and structural excavation and 112 m3 of mass and structural filling have been performed on Section 3c.
 


 

NOVEMBER 9TH-DECEMBER 8TH, 2010

• 1,717 m3 of mass and structural excavation and 1,696 m3 of mass and structural filling have been performed on Section 2b;
• 131 m3 of surface drainage concrete and 27 m3 of structural concrete have been placed on Section 2b;
• 1,143 m3 of ballast sub-base base have been produced on Section 3c;
• 271 m3 of structural concrete have been placed on Section 3c;
• 2,085 m3 of mass and structural excavation and 2,506 m3 of mass and structural filling have been performed on Section 3c.
 


 

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 
Multimedia Gallery
Press Release
Press Articles
Send a question
  • Autostrada Transilvania Project is a four-lane,...
more
Contact Site map Terms of use Privacy
Copyright Autostrada Transilvania 2008. All Rights Reserved.
Website by ROMNET