NOVEMBER 2008
• 141,964 m3 of mass and structural excavation and 145,333 m3 of mass and structural filling have been performed on Section 2B;
• 9,601 m3 of structural concrete was placed, including the production of 65 U-beams and the installation of 53 U-beams on Section 2B;
• 22,876 m3 of ballast sub-base, 12,272 m3 of crushed stone base and 11,339 tonnes of asphalt base course were installed on Section 2B;
• 118,688 m3 of mass and structural excavation and 140,989 m3 of mass and structural backfill have been performed on Section 3C;
• 1,283 LM of piles were cast and1,579 m3 of structural concrete was placed on Section 3C;
• 260,652 m3 of mass excavation and 286,322 m3 of mass fill have been performed on Section 2B and 3C.
|