JUNE 9TH- JULY 8TH 2009
• 333,942 m3 of mass and structural excavation and 727,574 m3 of mass and structural filling have been performed on Section 2B;
• 10,768 LM of piles were cast, 13,239 m3 of structural concrete placed, including the production of 112 U-beams, 55 T-beams and the installation of 48 T-beams and 50 U-beams on Section 2B;
• 44,334 m3 of ballast sub-base, 29,004 m3 of crushed stone base and 53,638 tonnes of asphalt base course were installed on Section 2B;
• 84,552 of ballast sub-base, 984 m3 of crushed stone base, 28,101 tonnes of asphalt aggregates have been produced on Section 2B.
|