DECEMBER 2008

• 4,777 m3 of mass and structural excavation and 7,965 m3 of mass and structural filling have been performed on Section 2B;
• 2,239 m3 of structural concrete was placed, including the production of 14 U-beams and the installation of 23 U-beams on Section 2B;
• 3,627 m3 of ballast sub-base, 45 m3 of crushed stone base and 4,819 tonnes of asphalt aggregates have been produced on Section 2B;
• 4,783 m3 of mass and structural excavation and 15,208 m3 of mass and structural backfill have been performed on Section 3C;
• 552 LM of piles were cast and 422 m3 of structural concrete was placed on Section 3C;
• 9,560 m3 of mass excavation and 23,173 m3 of mass fill have been performed on Section 2B and 3C.
 


 

NOVEMBER 2008

• 141,964 m3 of mass and structural excavation and 145,333 m3 of mass and structural filling have been performed on Section 2B;
• 9,601 m3 of structural concrete was placed, including the production of 65 U-beams and the installation of 53 U-beams on Section 2B;
• 22,876 m3 of ballast sub-base, 12,272 m3 of crushed stone base and 11,339 tonnes of asphalt base course were installed on Section 2B;
• 118,688 m3 of mass and structural excavation and 140,989 m3 of mass and structural backfill have been performed on Section 3C;
• 1,283 LM of piles were cast and1,579 m3 of structural concrete was placed on Section 3C;
• 260,652 m3 of mass excavation and 286,322 m3 of mass fill have been performed on Section 2B and 3C.
 


 

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 
Multimedia Gallery
Press Release
Press Articles
Send a question
  • Autostrada Transilvania Project is a four-lane,...
more
Contact Site map Terms of use Privacy
Copyright Autostrada Transilvania 2008. All Rights Reserved.
Website by ROMNET