OCTOBER 2008
• 189,992 m3 of mass and structural excavation and 196,927 m3 of mass and structural filling have been performed on Section 2B;
• 169 LM of piles were cast, 8,402 m3 of structural concrete placed, including the production of 58 U-beams and the installation of 40 U-beams on Section 2B;
• 32,023 m3 of ballast sub-base, 11,737 m3 of crushed stone base and 10,822 tonnes of asphalt base course were installed on Section 2B;
• 61,501 m3 of mass and structural excavation and 122,712 m3 of mass and structural backfill have been performed on Section 3C;
• 1,170 LM of piles were cast, 1,859 m3 of structural concrete placed which includes the production of 13 U-Beams on Section 3C;
• 251,493 m3 of mass excavation and 319,639 m3 of mass fill have been performed on Section 2B and 3C.
|