Construction Updates
OCTOBER 2008

• 189,992 m3 of mass and structural excavation and 196,927 m3 of mass and structural filling have been performed on Section 2B;
• 169 LM of piles were cast, 8,402 m3 of structural concrete placed, including the production of 58 U-beams and the installation of 40 U-beams on Section 2B;
• 32,023 m3 of ballast sub-base, 11,737 m3 of crushed stone base and 10,822 tonnes of asphalt base course were installed on Section 2B;
• 61,501 m3 of mass and structural excavation and 122,712 m3 of mass and structural backfill have been performed on Section 3C;
• 1,170 LM of piles were cast, 1,859 m3 of structural concrete placed which includes the production of 13 U-Beams on Section 3C;
• 251,493 m3 of mass excavation and 319,639 m3 of mass fill have been performed on Section 2B and 3C.
 


 

SEPTEMBER 2008

• 202, 447 m3 of mass and structural excavation and 321,891m3 of mass and structural filling have been performed on Section 2B;
• 944 LM of piles were cast, 7,993 m3 of structural concrete placed, including the production of 51 U-beams and the installation of 56 U-beams on Section 2B;
• 18,356 m3 of ballast sub-base, 3,618 m3 of crushed stone base and 28,370 tonnes of asphalt base course were installed on Section 2B;
• 82,492 m3 of mass and structural excavation and 81,993 m3 of mass and structural backfill have been performed on Section 3C;
• 1,395 LM of piles were cast, 4,629 m3 of structural concrete placed which includes the production of 28 U-Beams on Section 3C;
• 280,298 m3 of mass excavation and 401,818 m3 of mass fill have been performed on Section 2B and 3C.
 


 

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 
Multimedia Gallery
Press Release
Press Articles
Send a question
  • Autostrada Transilvania Project is a four-lane,...
more
Contact Site map Terms of use Privacy
Copyright Autostrada Transilvania 2008. All Rights Reserved.
Website by ROMNET