Construction Updates |
|
AUGUST 2008
- 307,340 m3 of mass and structural excavation and 292,558 m3 of mass and structural filling have been performed on Section 2B;
- 1,163 LM of piles were cast, 6,393 m3 of structural concrete placed, including the production of 54 U-beams and the installation of 56 U-beams on Section 2B;
- 6,201 m3 of ballast sub-base, 6,409 m3 of crushed stone base and 37,274 tonnes of asphalt base course were installed on Section 2B;
- 37,399 m3 of mass and structural excavation and 15,817 m3 of mass and structural backfill have been performed on Section 3C;
- 1,987 LM of piles were cast, 5,519 m3 of structural concrete placed which includes the production of 31 U-Beams on Section 3C;
- 345,339 m3 of mass excavation and 308,375 m3 of mass fill have been performed on Section 2B and 3C.
|
|
|
|
JULY 2008
- 232,427 m3 of mass and structural excavation and 216,729 m3 of mass and structural filling have been performed on Section 2B;
- 1,750 LM of piles installed, 9,499 m3 of structural concrete placed, including the production of 52 U-beams and the installation of 54 U-beams on Section 2B;
- 18,217 m3 of ballast, 13,854 m3 of crushed stone base and 927 tonnes of asphalt base course were installed on Section 2B;
- 2,519 m3 of mass and structural excavation and 2,736 m3 of mass and structural backfill have been performed on Section 3C;
- 777 LM of piles installed, 5,391 m3 of structural concrete placed which includes the production of 53 U-Beams on Section 3C;
- 38 piles were cast on section 2B and 48 on Section 3C;
- 234,946 m3 of mass excavation and 219,465 m3 of mass fill have been performed on Section 2B and 3C.
|
|
|
|