JUNE 2008

  • 137,472 m3 of mass and structural excavation and 227,211 m3 of mass and structural filling have been performed on Section 2B;
  • 840 LM of piles installed, 8,131 m3 of structural concrete placed, including the production of 53 U-beams and the installation of 36 U-beams on Section 2B;
  • 37,151 m3 of mass and structural excavation and 42,065 m3 of mass and structural backfill have been performed on Section 3C;
  • 869 LM of piles installed, 4,585 m3 of structural concrete placed which includes the production of 50 U-Beams on Section 3C;
  • 38 piles were cast on section 2B and 48 on Section 3C;
  • 159,705 m3 of mass excavation and 247,486 m3 of mass fill have been performed on Section 2B and 3C.
     

 

MAY 2008

  • 130,666 m3 of mass and structural excavation and 145,037 m3 of mass and structural filling have been performed on Section 2B;
  • 86,517 m3 of mass and structural excavation and 84,452 m3 of mass and structural backfill have been performed on Section 3C;
  • 14 T-Beams and 18 U-Beams produced on Section 3C;
  • 45 U-Beams produced and 20 installed on Section 2B;
  • 27 piles were cast on section 2B and 96 on Section 3C;
  • 187,908 m3 of mass excavation and 213,139 m3 of mass fill have been performed on Section 2B and 3C.

     

 

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 
Multimedia Gallery
Press Release
Press Articles
Send a question
  • Autostrada Transilvania Project is a four-lane,...
more
Contact Site map Terms of use Privacy
Copyright Autostrada Transilvania 2008. All Rights Reserved.
Website by ROMNET