Construction Updates
OCTOBER 9TH- NOVEMBER 8TH, 2010

• 33,083 m3 of mass and structural excavation and 29,060 m3 of mass and structural filling have been performed on Section 2b;
• 1,742 m3 of surface drainage concrete and 831 m3 of structural concrete have been placed on Section 2b; 22 LM of piles have been placed on Section 2b;
• 1,739 m3 of ballast sub-base and 208 m3 of crushed stone base have been produced; 575 m3 of ballast sub-base and 1,906 m3 of CSB have been installed on Section 2b;
• 4,325 tons of asphalt aggregates have been produced on Section 2b and 9,524 tons have been installed;
• 7,251 m3 of mass and structural excavation and 4,292 m3 of mass and structural filling have been performed on Section 3c;
• 12 U-beams have been produced and 32 have been installed; 2,965 m3 of structural concrete, 1,251 LM of piles have been placed on Section 3c.
 


 

SEPTEMBER 9TH- OCTOBER 8TH, 2010

• 25,742 m3 of mass and structural excavation and 43,121 m3 of mass and structural filling have been performed on Section 2b;
• 2,513 m3 of surface drainage concrete and 1,347 m3 of structural concrete have been placed on Section 2b;
• 8,491 m3 of ballast sub-base and 2,801m3 of crushed stone base have been produced; 12,786 m3 of ballast sub-base and 16,017 m3 of CSB have been installed on Section 2b;
• 42,830 tons of asphalt aggregates have been produced on Section 2b and 66,712 tons have been installed;
• 2,188 m3 of mass and structural excavation and 7,361 m3 of mass and structural filling have been performed on Section 3c;
• 22 U-beams have been produced and 4,264 m3 of structural concrete, 2,424 LM of piles have been placed on Section 3c.
 


 

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 
Multimedia Gallery
Press Release
Press Articles
Send a question
  • Autostrada Transilvania Project is a four-lane,...