SEPTEMBER 9TH- OCTOBER 8TH, 2010
• 25,742 m3 of mass and structural excavation and 43,121 m3 of mass and structural filling have been performed on Section 2b;
• 2,513 m3 of surface drainage concrete and 1,347 m3 of structural concrete have been placed on Section 2b;
• 8,491 m3 of ballast sub-base and 2,801m3 of crushed stone base have been produced; 12,786 m3 of ballast sub-base and 16,017 m3 of CSB have been installed on Section 2b;
• 42,830 tons of asphalt aggregates have been produced on Section 2b and 66,712 tons have been installed;
• 2,188 m3 of mass and structural excavation and 7,361 m3 of mass and structural filling have been performed on Section 3c;
• 22 U-beams have been produced and 4,264 m3 of structural concrete, 2,424 LM of piles have been placed on Section 3c.
|