Construction Updates
AUGUST 9TH-SEPTEMBER 8TH, 2010

• 35,404 m3 of mass and structural excavation and 45,532 m3 of mass and structural filling have been performed on Section 2b;
• 3,583 m3 of surface drainage concrete and 2,125 m3 of structural concrete have been placed on Section 2b;
• 53,825 m3 of ballast sub-base and 32,419 m3 of crushed stone base have been produced; 56,680 m3 of ballast sub-base and 49,132 m3 of CSB have been installed on Section 2b;
• 39,627 tons of asphalt aggregates have been produced on Section 2b and 71,486 tons have been installed;
• 10,750 m3 of mass and structural excavation and 8,833 m3 of mass and structural filling have been performed on Section 3c;
• 23 U-beams have been produced and 4,160 m3 of structural concrete, 2,496 LM of piles have been placed on Section 3c.
 


 

JULY 9TH-AUGUST 8TH, 2010

• 30,763 m3 of mass and structural excavation and 185,581 m3 of mass and structural filling have been performed on Section 2b;
• 3,561 m3 of surface drainage concrete and 3,504 m3 of structural concrete have been placed on Section 2b;
• 8 U-Beams have been installed on Section 2b;
• 37,311 m3 of ballast sub-base and 7,684 m3 of crushed stone base have been produced; 50,574 m3 of ballast sub-base and 21,662 m3 of CSB have been installed on Section 2b;
• 22,972 tons of asphalt aggregates have been produced on Section 2b and 39,374 tons have been installed;
• 7,255 m3 of mass and structural excavation and 1,695 m3 of mass and structural filling have been performed on Section 3c;
• 28 T-Beams and 19 U-beams have been produced and 2,347m3 of structural concrete, 720 LM of piles have been placed on Section 3c.
 


 

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 
Multimedia Gallery
Press Release
Press Articles
Send a question
  • Autostrada Transilvania Project is a four-lane,...
more
Contact Site map Terms of use Privacy
Copyright Autostrada Transilvania 2008. All Rights Reserved.
Website by ROMNET