AUGUST 9TH-SEPTEMBER 8TH, 2010
• 35,404 m3 of mass and structural excavation and 45,532 m3 of mass and structural filling have been performed on Section 2b;
• 3,583 m3 of surface drainage concrete and 2,125 m3 of structural concrete have been placed on Section 2b;
• 53,825 m3 of ballast sub-base and 32,419 m3 of crushed stone base have been produced; 56,680 m3 of ballast sub-base and 49,132 m3 of CSB have been installed on Section 2b;
• 39,627 tons of asphalt aggregates have been produced on Section 2b and 71,486 tons have been installed;
• 10,750 m3 of mass and structural excavation and 8,833 m3 of mass and structural filling have been performed on Section 3c;
• 23 U-beams have been produced and 4,160 m3 of structural concrete, 2,496 LM of piles have been placed on Section 3c.
|