JUNE 9TH- JULY 8TH, 2010
• 120,761 m3 of mass and structural excavation and 512,018 m3 of mass and structural filling have been performed on Section 2b;
• 3,482 m3 of surface drainage concrete and 3,473 m3 of structural concrete have been placed on Section 2b;
• 35 T-Beams have been installed on Section 2b;
• 17,164 m3 of ballast sub-base and 15,536 m3 of crushed stone base have been produced; 17,980 m3 of ballast sub-base and 10,319 m3 of CSB have been installed on Section 2b;
• 6,815 tons of asphalt aggregates have been produced on Section 2b;
• 21,742 m3 of mass and structural excavation and 840 m3 of mass and structural filling have been performed on Section 3c;
• 30 T-Beams and 21 U-beams have been produced and 1,461m3 of structural concrete, 1,891 LM of piles have been placed on Section 3c.
|