Construction Updates
JUNE 9TH- JULY 8TH, 2010

• 120,761 m3 of mass and structural excavation and 512,018 m3 of mass and structural filling have been performed on Section 2b;
• 3,482 m3 of surface drainage concrete and 3,473 m3 of structural concrete have been placed on Section 2b;
• 35 T-Beams have been installed on Section 2b;
• 17,164 m3 of ballast sub-base and 15,536 m3 of crushed stone base have been produced; 17,980 m3 of ballast sub-base and 10,319 m3 of CSB have been installed on Section 2b;
• 6,815 tons of asphalt aggregates have been produced on Section 2b;
• 21,742 m3 of mass and structural excavation and 840 m3 of mass and structural filling have been performed on Section 3c;
• 30 T-Beams and 21 U-beams have been produced and 1,461m3 of structural concrete, 1,891 LM of piles have been placed on Section 3c.
 


 

MAY 9TH-JUNE 8TH, 2010

• 190,148 m3 of mass and structural excavation and 414,369 m3 of mass and structural filling have been performed on Section 2b;
• 2,314 m3 of surface drainage concrete and 2,167 m3 of structural concrete have been placed on Section 2b;
• 36 T-Beams have been installed on Section 2b;
• 22,468 m3 of ballast sub-base and 4,350 m3 of crushed stone base have been installed and 10,324 m3 of CSB have been produced on Section 2b;

 


 

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 
Multimedia Gallery
Press Release
Press Articles
Send a question
  • Autostrada Transilvania Project is a four-lane,...
more
Contact Site map Terms of use Privacy
Copyright Autostrada Transilvania 2008. All Rights Reserved.
Website by ROMNET