APRIL 9TH - MAY 8TH, 2010
•70,821 m3 of mass and structural excavation and 128,287 m3 of mass and structural filling have been performed on Section 2b;
• 580 m3 of surface drainage concrete, 1,534 m3 of structural concrete and 483 lm of piles have been placed on Section 2b.
• 2,642 m3 of ballast sub-base have been installed and 3,356 m3 of crushed stone base have been produced on Section 2b;
|