Construction Updates
FEBRUARY 9TH-MARCH 8TH, 2010

• 10,608 m3 of mass and structural excavation and 4,250 m3 of mass and structural filling have been performed on Section 2b;
• 57m3 of surface drainage concrete and 1,287 structural concrete have been placed on Section 2b;
• 18T-Beams have been produced on Section 2b.
 


 

JANUARY 9TH-FEBRUARY 8TH, 2010

• 3,896 m3 of mass and structural excavation and 5,508 m3 of mass and structural filling have been performed on Section 2b;
• 36 T-Beams have been installed on Section 2b;
• 1,113 m3 of structural concrete have been placed and 784 lm of piles have been installed on Section 2b;
• 586 m3 of mass and structural excavation have been performed on Section 3c;
• 9 T-Beams and 18 U-Beams have been produced on Section 3c;
• 824 m3 of structural concrete have been placed on Section 3c.
 


 

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 
Multimedia Gallery
Press Release
Press Articles
Send a question
  • Autostrada Transilvania Project is a four-lane,...
more
Contact Site map Terms of use Privacy
Copyright Autostrada Transilvania 2008. All Rights Reserved.
Website by ROMNET