NOVEMBER 9TH-DECEMBER 8TH
• 54,886 m3 of mass and structural excavation and 138,466 m3 of mass and structural filling have been performed on Section 2b;
• 13,960 m3 of surface drainage concrete and 2,517 m3 structural concrete placed on Section 2b;
• 5,814 m3 of ballast sub-base, 21,553 m3 of crushed stone base and 46,687 tonnes of asphalt base course were installed on Section 2b;
• 3,234 m3 of ballast sub-base, 16,124 m3 of crushed stone base, 16,268 tonnes of asphalt aggregates have been produced on Section 2b;
• 37,385 m3 of mass and structural excavation and 32,058 m3 of mass and structural filling have been performed on Section 3c;
• 126 U-Beams have been installed, 27 U-Beams produced, 1,938 m3 of surface drainage concrete and 2,153 m3 of structural concrete placed, 500 lm of piles have been installed on Section 3c.
|