Construction Updates
JUNE 9TH- JULY 8TH 2009

• 333,942 m3 of mass and structural excavation and 727,574 m3 of mass and structural filling have been performed on Section 2B;
• 10,768 LM of piles were cast, 13,239 m3 of structural concrete placed, including the production of 112 U-beams, 55 T-beams and the installation of 48 T-beams and 50 U-beams on Section 2B;
• 44,334 m3 of ballast sub-base, 29,004 m3 of crushed stone base and 53,638 tonnes of asphalt base course were installed on Section 2B;
• 84,552 of ballast sub-base, 984 m3 of crushed stone base, 28,101 tonnes of asphalt aggregates have been produced on Section 2B.
 


 

MAY 9TH-JUNE 8TH, 2009

• 450,207 m3 of mass and structural excavation and 462,639 m3 of mass and structural filling have been performed on Section 2B;
• 5,543 LM of piles were cast, 11,920 m3 of structural concrete placed, including the production of 85 U-beams and the installation of 21 T-beams and 78 U-beams on Section 2B;
• 57,585 m3 of ballast sub-base, 26,224 m3 of crushed stone base and 36,016 tonnes of asphalt base course were installed on Section 2B;
• 59,428 of ballast sub-base, 7,576 m3 of crushed stone base, 32,153 tonnes of asphalt aggregates have been produced on Section 3C.
 


 

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 
Multimedia Gallery
Press Release
Press Articles
Send a question
  • Autostrada Transilvania Project is a four-lane,...
more
Contact Site map Terms of use Privacy
Copyright Autostrada Transilvania 2008. All Rights Reserved.
Website by ROMNET