Construction Updates
DECEMBER 9TH, 2009-JANUARY 8, 2010

• 4,690 m3 of mass and structural excavation and 2,960 m3 of mass and structural filling have been performed on Section 2b;
• 132 m3 of surface drainage concrete and 269 m3 of structural concrete have been placed on Section 2b;
• 1,508 lm of piles have been installed on Section 2b;
• 1,324 m3 of mass and structural excavation has been performed on Section 3c;
• 15 U-Beams have been produced and 375 m3 of structural concrete has been placed on Section 3c.
 


 

NOVEMBER 9TH-DECEMBER 8TH

• 54,886 m3 of mass and structural excavation and 138,466 m3 of mass and structural filling have been performed on Section 2b;
• 13,960 m3 of surface drainage concrete and 2,517 m3 structural concrete placed on Section 2b;
• 5,814 m3 of ballast sub-base, 21,553 m3 of crushed stone base and 46,687 tonnes of asphalt base course were installed on Section 2b;
• 3,234 m3 of ballast sub-base, 16,124 m3 of crushed stone base, 16,268 tonnes of asphalt aggregates have been produced on Section 2b;
• 37,385 m3 of mass and structural excavation and 32,058 m3 of mass and structural filling have been performed on Section 3c;
• 126 U-Beams have been installed, 27 U-Beams produced, 1,938 m3 of surface drainage concrete and 2,153 m3 of structural concrete placed, 500 lm of piles have been installed on Section 3c.
 


 

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 
Multimedia Gallery
Press Release
Press Articles
Send a question
  • Autostrada Transilvania Project is a four-lane,...
more
Contact Site map Terms of use Privacy
Copyright Autostrada Transilvania 2008. All Rights Reserved.
Website by ROMNET