Construction Updates
APRIL 9TH-MAY 8TH, 2009

• 327,292 m3 of mass and structural excavation and 198,682 m3 of mass and structural filling have been performed on Section 2B;
• 1,489 LM of piles were cast, 7,437 m3 of structural concrete placed, including the production of 50 U-beams and the installation of 55 U-beams on Section 2B;
• 27,474 m3 of ballast sub-base, 20,330 m3 of crushed stone base and 20,978 tonnes of asphalt base course were installed on Section 2B;
• 18,881 m3 of crushed stone base and 1,598 tonnes of asphalt aggregates have been produced on Section 3C.
 


 

MARCH 9TH-APRIL 8TH, 2009

•4,635 m3 of mass and structural excavation and 3,425 m3 of mass and structural filling have been performed on Section 2B;
•1,821 m3 of structural concrete placed which includes the production of 24 U-Beams on Section 2B;
•304 m3 of ballast sub-base were produced and 3,395 m3 were installed on Section 2B;
•12,010 tonnes of asphalt aggregates have been produced on Section 3C.
 


 

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 
Multimedia Gallery
Press Release
Press Articles
Send a question
  • Autostrada Transilvania Project is a four-lane,...
more
Contact Site map Terms of use Privacy
Copyright Autostrada Transilvania 2008. All Rights Reserved.
Website by ROMNET