SEPTEMBER 9TH-OCTOBER 8TH 2009
• 543,516 m3 of mass and structural excavation and 531,795 m3 of mass and structural filling have been performed on Section 2B;
• 555 LM of piles were cast, 18,555 m3 of structural concrete placed, including the production of 16 U-beams, 16 T-beams and the installation of 36 T-beams and 176 U-beams on Section 2B;
• 116,331 m3 of ballast sub-base, 78,026 m3 of crushed stone base and 164,575 tonnes of asphalt base course were installed on Section 2B;
• 103,350 m3 of ballast sub-base, 2,606 m3 of crushed stone base, 40,414 tonnes of asphalt aggregates have been produced on Section 2B;
• 74,573 m3 of mass and structural excavation and 145,984 m3 of mass and structural filling have been performed on Section 3C;
• 723 LM of piles were cast, 5 T-beams and 40 U-Beams installed, 21 U-Beams produced, 1,210 m3 of structural concrete placed, 666 m3 of crushed stone base have been produced on Section 3C.
|