APRIL 9TH-MAY 8TH, 2009
• 327,292 m3 of mass and structural excavation and 198,682 m3 of mass and structural filling have been performed on Section 2B;
• 1,489 LM of piles were cast, 7,437 m3 of structural concrete placed, including the production of 50 U-beams and the installation of 55 U-beams on Section 2B;
• 27,474 m3 of ballast sub-base, 20,330 m3 of crushed stone base and 20,978 tonnes of asphalt base course were installed on Section 2B;
• 18,881 m3 of crushed stone base and 1,598 tonnes of asphalt aggregates have been produced on Section 3C.
|