Construction Updates
AUGUST 9TH - SEPTEMBER 8TH 2009

• 573,462 m3 of mass and structural excavation and 692,814 m3 of mass and structural filling have been performed on Section 2B;
• 1,931 LM of piles were cast, 19,135 m3 of structural concrete placed, including the production of 63 U-beams, 11 T-beams and the installation of 98 T-beams and 169 U-beams on Section 2B;
• 105,580 m3 of ballast sub-base, 46,201 m3 of crushed stone base and 103,469 tonnes of asphalt base course were installed on Section 2B;
• 77,081 m3 of ballast sub-base, 6,545 m3 of crushed stone base, 9,390 tonnes of asphalt aggregates have been produced on Section 2B;
• 23,276 m3 of mass and structural excavation and 11,475 m3 of mass and structural filling have been performed on Section 3C;
• 480 LM of piles were cast, 1,387 m3 of structural concrete placed, 1,589 m3 of ballast sub-base, 14,965 tonnes of asphalt aggregates have been produced on Section 3C.
 


 

JULY 9TH- AUGUST 8TH 2009

•498,013 m3 of mass and structural excavation and 813,112 m3 of mass and structural filling have been performed on Section 2B;
• 1,042 LM of piles were cast, 15,808 m3 of structural concrete placed, including the production of 120 U-beams, 29 T-beams and the installation of 37 T-beams and 112 U-beams on Section 2B;
• 70,157 m3 of ballast sub-base, 34,163 m3 of crushed stone base and 54,485 tonnes of asphalt base course were installed on Section 2B;
• 60,395 of ballast sub-base, 2,005 m3 of crushed stone base, 9,100 tonnes of asphalt aggregates have been produced on Section 2B;
• 380 LM of piles were cast, 1,448 m3 of structural concrete placed and 26,781 tonnes of asphalt aggregates have been produced on Section 3C.
 


 

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 
Multimedia Gallery
Press Release
Press Articles
Send a question
  • Autostrada Transilvania Project is a four-lane,...
more
Contact Site map Terms of use Privacy
Copyright Autostrada Transilvania 2008. All Rights Reserved.
Website by ROMNET