AUGUST 9TH - SEPTEMBER 8TH 2009
• 573,462 m3 of mass and structural excavation and 692,814 m3 of mass and structural filling have been performed on Section 2B;
• 1,931 LM of piles were cast, 19,135 m3 of structural concrete placed, including the production of 63 U-beams, 11 T-beams and the installation of 98 T-beams and 169 U-beams on Section 2B;
• 105,580 m3 of ballast sub-base, 46,201 m3 of crushed stone base and 103,469 tonnes of asphalt base course were installed on Section 2B;
• 77,081 m3 of ballast sub-base, 6,545 m3 of crushed stone base, 9,390 tonnes of asphalt aggregates have been produced on Section 2B;
• 23,276 m3 of mass and structural excavation and 11,475 m3 of mass and structural filling have been performed on Section 3C;
• 480 LM of piles were cast, 1,387 m3 of structural concrete placed, 1,589 m3 of ballast sub-base, 14,965 tonnes of asphalt aggregates have been produced on Section 3C.
|