Construction Updates
JANUARY 9TH-FEBRUARY 8TH, 2010

• 3,896 m3 of mass and structural excavation and 5,508 m3 of mass and structural filling have been performed on Section 2b;
• 36 T-Beams have been installed on Section 2b;
• 1,113 m3 of structural concrete have been placed and 784 lm of piles have been installed on Section 2b;
• 586 m3 of mass and structural excavation have been performed on Section 3c;
• 9 T-Beams and 18 U-Beams have been produced on Section 3c;
• 824 m3 of structural concrete have been placed on Section 3c.
 


 

DECEMBER 9TH, 2009-JANUARY 8, 2010

• 4,690 m3 of mass and structural excavation and 2,960 m3 of mass and structural filling have been performed on Section 2b;
• 132 m3 of surface drainage concrete and 269 m3 of structural concrete have been placed on Section 2b;
• 1,508 lm of piles have been installed on Section 2b;
• 1,324 m3 of mass and structural excavation has been performed on Section 3c;
• 15 U-Beams have been produced and 375 m3 of structural concrete has been placed on Section 3c.
 


 

1 2 3 4 5 6 7 8 9 10 11 12 13 
Multimedia Gallery
Press Release
Press Articles
Send a question
  • Autostrada Transilvania Project is a four-lane,...
more
Contact Site map Terms of use Privacy
Copyright Autostrada Transilvania 2008. All Rights Reserved.
Website by ROMNET